Barnsley's Programme

bsf - Roofdeck.jpg

Barnsley will be amongst the first 30 areas in the country to benefit from 'Building Schools for the Future' - the biggest single government investment in improving school buildings for over 50 years.

This Department for Children, Schools and Families (DCSF) programme aims to raise educational attainment by rebuilding or renewing every secondary school in England over the next 10 to 15 years. Subject to future spending reviews, the government will allocate £2.2 billion capital expenditure each year to the programme in order to give students access to world class, 21st Century learning environments that will inspire teachers and learners for decades to come. 

This once in a lifetime initiative will:

  • reorganise secondary school and ICT provision to have the greatest possible effect on pupil achievement
  • promote better school design
  • make procurement more efficient
  • link with other funding to achieve greater community use of schools

Background

Barnsley secondary schools achieved their best ever GCSE results in 2009. Five plus A*-C GCSE grades, including English and mathematics, rose from 33.1% in 2008 to 39.3% in 2009, a 6.2% gain across the local authority.  This committed effort to raise attainment means Barnsley local authority is the ninth most improved local authority in the country.  Five plus A*-C GCSE grades rose from 55.8% in 2008 to 60.5% in 2009, a 4.7% gain.

However, despite these improvements, attainment in Barnsley remains well below national averages, and the numbers of young people entering post sixteen learning stands at 63%. When combined with other facts, such as the number of children living in poverty, health outcomes, progression rates etc, the need for change becomes clear. These priorities are set out in the Children and Young People’s Plan (CYPP), which puts the development of localised, integrated service delivery, based at our new Advanced Learning Centres, at the heart of our strategy.

Barnsley’s Remaking Learning Vision has been the subject of widespread consultation with the whole community. It describes a process of systemic and transitional change to transform learning in the whole of the Borough, by creating the conditions and context for change for all of our schools to deliver higher standards, better outcomes for children and young people, and better quality learning for all. Our consultation continues with pupils, parents, community, staff and governors, through the CYPP process, the overall BSF programme plan and the design process for each ALC.

The Strategic Business Case sets out in full the education vision that underlies the BSF programme, and together with the Outline Business Case, gives more details on all the areas covered below. back to top

The project

Barnsley is replacing its entire secondary school estate by the new build of nine ALCs. In addition Barnsley proposes the new build of one new special school and the replacement of a substantial part of one existing special school with the remainder of the school being retained estate. 

The schools involved in this programme are:

New build replacement ALCs built on their existing sites

New build replacement ALCs to be built at new sites to accommodate reorganised schools

New build special school and new build extensions to existing special school

Penistone Grammar Royston and Edward Sheerien Springwell Community Special
Kirk Balk Kingstone and Holgate Greenacre Special
The Dearne Wombwell and Foulstone
Darton Priory and Willowgarth
St Michael's

Each ALC will offer full service provision, be open up to 48 weeks a year, have a dispersed pupil referral unit (PRU) attached to it and offer provision for adult and community learning.

Seven of these ALCs will be procured through PFI funding and two through traditional design and build. The new special school will be PFI funded and the extension to the existing special school will be design and build.

The capital costs of the programme are in the region of £300 million and the revenue cost over the contract period will exceed
£1 billion.

There have been no changes to the corporate and education strategy since submission of the SBC. The estates strategy has changed to reflect phasing and the number of sample schemes to be negotiated on and this is reflected in the table below.

SBC

OBC

ALC

Phase

Type of Build

Procurement Route

Phase

Type of Build

Procurement Route

Edward Sheerien/
Royston High

1
(Sample Scheme)

New Build

PFI

1
(Sample Scheme

New Build

Traditional

Penistone Grammar

1
(Sample Scheme)

New Build

PFI

1
(Sample Scheme)

New Build

PFI

The Dearne High

1
(Sample Scheme)

New Build

Traditional

1
(Sample Scheme)

New Build

Traditional

Kirk Balk

2/1R

New Build

Traditional

1
(Sample Scheme)

New Build

PFI

Darton

2/1R

New Build

PFI

1

New Build

PFI

Willowgarth/Priory

2

New Build

PFI

2

New Build

PFI

Springwell Community (SEN)

3

New Build

PFI

2

New Build

PFI

Greenacre (SEN)

2

New Build

Traditional

2

New Build

Traditional

Foulstone/Wombwell

3

New Build

PFI

3

New Build

PFI

St Michael's Catholic
and CE High

3

New Build

PFI

3

New Build

PFI

The Kingstone/Holgate

3

New Build

PFI

3

New Build

PFI

back to top

Procurement strategy 

Barnsley is unique in its approach to its Building Schools for the Future Project as it is replacing its entire secondary school estate with new build ALCs and new SEN facilities and the Borough itself is making a large funding commitment to this project on an ongoing basis.  Barnsley aims to ensure that every school is delivered to a high design specification to achieve its learning agenda and on that basis the Private Sector Partner must be able to fulfil the demands required.

The ALCs will be delivered in a single wave which will be split into three phases. The wave will include a mixture of PFI and conventionally funded design and build contracts.  Every ALC will be treated the same in relation to such issues as both hard and soft facilities management.  This is to ensure that the ALCs will have longevity, achieve respect and become a meaningful resource, not only for the secondary and special school function but also for the wider community.  The contractual and procurement documentation which will be used will be PfS standard form documentation or as near to the form standard as will be agreed with Partnerships for Schools to ensure that the ultimate aim is achieved including the following:

  • Template ITN/ITCD documentation
  • Template output specification for PFI, D&B and ICT
  • Strategic Partnering Agreement
  • Shareholders' Agreement
  • PFI Contract
  • Design and Build Contract
  • ICT Services Contract
  • VA documentation

The borough is proposing to adopt a structure to enable delivery of the BSF programme in the most effective manner possible to ensure value for money.

To achieve Barnsley’s transformational aims it has created a Local Education Partnership (LEP) based on the Partnerships for Schools’ model.  The facilities management of all ALCs (both Design and Build and PFI) and ICT provision to all ALCs will be undertaken through the LEP. Views on the LEP were taken at the soft market testing events and it was clear that the market considered the LEP model appropriate for Barnsley. back to top

Local Education Partnership

Barnsley is committed to the Local Education Partnership (LEP) model, whereby the programme will be delivered through a joint venture company in which a private sector partner has the majority of shares and Barnsley and Partnerships for Schools are also shareholders. Barnsley believes this will help to embed long-term partnership working.  The facilities management of all ALCs excluding catering (both Design and Build and PFI) and ICT provision to all ALCs will be undertaken through the LEP.

Our private sector partner was selected on the basis of robust criteria.  Barnsley has at the heart of our BSF Project a commitment to the borough wide remaking learning agenda and a true belief in the Every Child Matters agenda.  These issues and the ability of our private sector partner to work within the ethos of the partnership were the cornerstone of the selection process.  The terms of exclusivity will be determined in consultation with Partnerships for Schools to ensure that the best outcomes are achieved for the Project. back to top

ICT services contract

The ICT services contract will be based on the standard PfS ICT output specification.  The aim of the managed service is to deliver and support the ICT provision to enable the learning objectives to be met.  In practice this entails ensuring that the ICT equipment and associated software and data are fit for purpose, available for use during the school opening contract hours and that a comprehensive help desk capability exists to support the ALC.

A key point of focus during Barnsley’s assessment of the bids will be the degree to which the ICT element of a bidder’s proposal is influencing the building design.  Therefore, the council will be looking for evidence of genuine partnership between the ICT provider and the other parts of each consortium.  The consortium will be able to produce evidence of its ability and willingness to combine a talent for innovative building design with knowledge of how ICT can be used to transform learning outcomes. back to top

Facilities management services

Facilities management, with the exception of catering, will be included in the PFI contracts. In the case of two ALCs and one special school procured under the standard Design and Build agreements the council intends to seek agreement with the PFI facilities management provider for the provision of FM and lifecycle costs to the same standard as in the PFI schools. back to top

Financial issues
 
Value for money

The council has undertaken a value for money assessment in accordance with HM Treasury(August 2004) and PfS guidance which indicates that that procurement of seven of the ALCs and one special school by a PFI contract will deliver better VFM when compared with procurement by traditional public sector procurement mechanisms.  This has been ratified by its financial advisors Deloitte.  A similar assessment carried out on the remaining two ALCs and one special school also indicates that procurement through a PFI contract would be better value for money but as PFI credits are unavailable for the whole of the wave a PFI procurement route for these would be unaffordable.

 Affordability

The programme will cost significantly more in both capital and revenue terms than provided by the government though the capital funding envelope or in PFI credit grant.

The capital cost of the programme is approximately £300 million and the revenue cost over the contract period will exceed £1 billion.

The council has resolved to contribute a minimum of £5m a year (inflated) towards funding the excess capital and revenue costs.

In addition as significant annual savings can be made by schools owing to the proposal to reduce the number of schools from 13 to nine ALCs,  Schools  Forum has agreed to contribute this annual sum (£3.1m each year inflated over the period of the contracts) towards meeting the costs of provision over and above the funding provided by the government and the Council

On the current basis the programme is within the council’s affordability ceiling. 

Further information

Further information on financial issue is given in sections 5 and 6 of the OBC. back to top

Readiness to deliver

Barnsley is confident of its ability to procure and manage this programme and has the necessary experience and resources set up to procure the first and subsequent phases and support them through resulting PFI and traditional contracts.

Barnsley has successfully procured and managed a recent PFI primary school programme and this experienced team has been retained to be the core of a larger BSF core team. Lessons learnt from this experience will guide the BSF process. The programme team and support structure is appropriately resourced, dedicated and with an experienced and skilled mix of individuals.

The authority has unprecedented support of the programme and has commitment from Cabinet and stakeholders to fund the scheme well above the PfS funding allocation.  Significant funding has been made available for the support programme delivery team throughout the procurement process and during the delivery of further phases and the contract support phase. back to top
 
Leading and managing change

Barnsley is committed to the transformational agenda fundamental to BSF and recognises that the project is not only about buildings, but also about changing how learning is facilitated and delivered.  The structures in the project have and will continue to have engagement with stakeholders at the centre with a clear focus on the contribution each can make to the transformation.  This engagement has had at its core work with the schools to guide and support them as they consider the issues about learning and begin to describe the activities that will truly transform and will guide the development of the new buildings.  This has been exemplified in the schools design and brief development workshops.

We are keen to develop the LEP as a true partner who will engage with the wider aspirations of the council as the remaking learning agenda plays its part in the wider remaking Barnsley agenda.  This partnership will establish and use the Local Education Partnership as the vehicle for design, construction, equipping, servicing and continuous improvement of learning environments.

Since the LEP came into being it has demonstrated its commitment to Barnsley's transformational agenda through its 'added value' plan, which includes a commitment to taking on 40 apprentices, a range of learning activities around construction and engineering for current school students, and support for teachers' development. back to top

Key milestones and programme timetable

 KEY MILESTONES  
 Education vision approved  15 December 2006
 Strategic Business Case approved   15 December 2006
 Outline Business Case approval from Project Review Group received      15 March 2007
 OJEU Notice issued   16 March 2007
 Bidder longlist of five selected  17 May 2007
 Issue Invitation to Participate in Dialogue (ITPD)  18 May 2007
 Bidder shortlist of three selected   21 June 2007
 After design of sample schemes and evaluation of bids, number of bidders reduced to two  23 January 2008
 Dialogue continues until  19 September 2008   
 PROGRAMME TIMETABLE TO COMPLETION
 Final bids received and evaluated by  November 2008
 Appoint preferred bidder  November 2008
 Complete final business case  March 2009
 Financial close   June 2009
 Start Phase 1    June 2009
 Complete supplementary business case  1  January 2009
 Start Phase 2     March 2010
 Complete supplementary business case 2  September 2009
 Start Phase 3        November 2010
 Complete Phase 1  April 2011
 Complete Phase 2    September 2011
 Complete Phase 3    September 2012

               

        

       

 

 

 

  